All tagged Scenic Drive Stabilization

Scenic Dr. to get final phase of stabilization; Logging set for Dog River Pipeline

The stabilization work has been ongoing since 2015 in an effort to prevent the embankment to the north of Scenic Drive road from falling. Stabilization Improvements to an approximate 1/4 mile segment of between Jefferson Street/Terrace Drive and Esther Way are mostly complete. Project Engineer Mike Bosse said the latest phase will be completed by the end of October in four areas in the ¼ mile stretch with four different sections measuring, 110, 45, 40, and 70 feet.