TD Council accelerates utility project on Webber St.; 7-day work week aims to bring project to end 9 days early
City leaders approve seven-day work schedule at a cost of $118,00 to shorten project timeline. Full Webber Street closure will continue through June 26, impacting access to port businesses.
Pub pushes to reopen Webber Street as TD council approves archaeology contract, funding changes
Webber Street closure concerns dominate as business reports steep loss, while The Dalles council approves a $146K archaeology contract and shifts nonprofit funding process.
Webber Street Reopens Early: City of TD and Contractor Find Solution to Keep Business Access Open
Webber Street has reopened for the weekend, restoring access to Port-area businesses as the city prepares a new traffic plan tied to the Westside Interceptor project.